1st DownTown April Update

1st DownTown April Update

THE GRASS IS ALWAYS GREENER… AT MILLER ELECTRIC CENTER! With the irrigation system framework in place, Miller Electric Center’s outdoor practice fields natural turf installation is taking shape. Nearly 1,000 rolls of sod weighing in at roughly 820 tons were laid...
1st DownTown March Update

1st DownTown March Update

A BUSY MONTH FOR MILLER ELECTRIC CENTER On March 8, Miller Electric Center’s construction manager, Haskell, treated all 500+ site workers to an appreciation lunch, raffle prizes, high-visibility performance t-shirts, plus surprise guest appearances by Jaguars...
1st DownTown February Update

1st DownTown February Update

MOVEMENT AT MILLER ELECTRIC CENTER Work continues! A concrete pump arrived onsite to pour the retaining wall and hardscape at MEC’s entry plaza. Hanging field goal posts recently went up at the indoor practice field, as well as catch nets. Coach Pederson and the...
1st DownTown January Update

1st DownTown January Update

A YEAR OF MEC January 10 marked one year since construction began on the Miller Electric Center, the Jacksonville Jaguars’ training facility. Work is currently underway on the interior buildout. Exterior framing continues with glass going up and weather barrier...
1st DownTown November Update

1st DownTown November Update

CONSTRUCTION WITH COACH AT MILLER ELECTRIC CENTER Jaguars Head Coach Doug Pederson and General Manager Trent Baalke recently toured the Miller Electric Center to see the sports performance center’s construction progress. “It is obvious that so much care and expertise...